The project involved the construction of an expressway on the section between the “Skrudki Interchange” (excluding the interchange) and the “Sielce Interchange,” now called “Kurów Zachód” (excluding the interchange), along with engineering structures and associated infrastructure
Approx. 13.17 km
270,000,000 PLN / 64,285,714.29 EUR
(1 EUR = 4.20 PLN)
GDDKiA Lublin
The project involved the construction of an expressway on the section between the “Skrudki Interchange” (excluding the interchange) and the “Sielce Interchange,” now “Kurów Zachód” (excluding the interchange), along with engineering structures and associated infrastructure. The completed road section is approximately 13.17 km in length.